Construction Law, Contract Administration

Termination under FIDIC: For Cause and For Convenience under Clauses 15 and 16 (1999 vs 2017)

Termination is the most drastic remedy available under any construction contract, and the FIDIC forms are no exception. Bringing a contract to a premature end exposes both parties to substantial financial consequences, demobilisation costs, claims for loss of profit, and frequently protracted disputes over whether the termination was lawful in the first place. The FIDIC suite addresses termination through two parallel regimes — Clause 15, which governs termination by the Employer, and Clause 16, which governs suspension and termination by the Contractor. A wrongful termination can convert the terminating party from an aggrieved innocent into a repudiating defendant overnight, so the procedural discipline these clauses demand is not optional ceremony but the very thing that determines who wins.

Construction Law, Contract Administration

The Engineer’s Role in Dispute Prevention: Agreement and Determination under FIDIC Sub-Clause 3.7 (2017)

One of the most significant structural changes in the FIDIC 2017 suite is the formalisation of the Engineer’s role in resolving disagreements between the Employer and Contractor before they escalate into formal disputes. Under Sub-Clause 3.7 of the 2017 Red, Yellow, and Silver Books, the Engineer is now required to follow a two-stage process — first attempting to facilitate an agreed settlement, and then, if agreement is not reached, issuing a formal Determination. This structured mechanism replaces the relatively brief Sub-Clause 3.5 of the 1999 editions and reflects a deliberate policy decision by FIDIC to embed dispute prevention into the contractual administration framework. Understanding how this process works — and where it can go wrong — is essential for every Engineer, Contractor, and Employer working on FIDIC projects.

Construction Law, Contract Administration

Force Majeure Under FIDIC: From “Force Majeure” to “Exceptional Events” — What Changed and Why It Matters

Few provisions in construction contracts generate as much controversy as force majeure — the clause that allocates risk when circumstances beyond any party’s control bring a project to its knees. Under the FIDIC 1999 suite, Clause 19 addressed “Force Majeure” in familiar, if imprecise, terms. The FIDIC 2017 editions deliberately rebranded the entire mechanism as “Exceptional Events” under Clause 18, a change that is more than cosmetic. The 2017 amendments introduce tighter procedural requirements, recalibrate the entitlement to additional time and money, and redefine what qualifies as a triggering event. For contractors, employers, and engineers working on international projects today, understanding the differences between these two regimes is not a matter of academic interest — it is a matter of contractual survival.

Construction Law, Contract Administration

Variations Under FIDIC Clause 13: Instructed Variations, Constructive Variations, and Value Engineering

Variations are among the most commercially significant events on any FIDIC-governed project. The right to instruct variations sits at the core of the Employer’s contractual power, yet the mechanism is far from one-sided. FIDIC Clause 13 — in both the 1999 and 2017 editions of the Red, Yellow, and Silver Books — creates a comprehensive framework governing how variations are initiated, valued, and paid. Understanding this framework is essential for contractors seeking fair compensation, engineers administering change fairly, and employers controlling scope and cost. Mismanaging the variation process is one of the most common sources of dispute on major infrastructure and building projects worldwide.

Construction Law, Contract Administration

FIDIC Payment Provisions: The IPC Process, Withholding, Set-Off, and Late Payment Interest

Payment is the lifeblood of any construction project, yet the FIDIC payment mechanism — in both the 1999 and 2017 suites — is among the most technically demanding and frequently disputed aspects of contract administration. From the preparation of the Interim Payment Certificate (IPC) and the Engineer’s power to withhold or correct amounts, to the Employer’s right of set-off and the contractor’s entitlement to financing charges on late payments, the payment clauses contain traps for the unwary on all sides. Understanding precisely how the mechanism operates, and where it commonly fails, is essential for contractors, employers, and engineers alike.

Construction Law, Contract Administration

Unforeseeable Ground Conditions Under FIDIC Sub-Clause 4.12: The Objective Test and What Contractors Must Prove

Ground conditions have derailed more construction projects — and generated more claims — than almost any other single factor. When a contractor breaks ground and encounters rock where soil surveys suggested soft earth, or strikes an abandoned utilities network that no map recorded, or finds groundwater at depths that make excavation a different project entirely, the question of who bears the cost is rarely straightforward. FIDIC Sub-Clause 4.12 is the contractual mechanism designed to answer that question — but its application turns on a deceptively difficult concept: what an “experienced contractor” could reasonably have foreseen. Understanding how that test works in practice is essential for every party operating under a FIDIC contract.

Construction Law, Contract Administration

The FIDIC 2017 Claims Mechanism: Has the Time-Bar Beast Been Tamed?

Of all the contentious provisions in international construction contracts, few have generated more disputes — or more anxiety among contractors — than the 28-day notice requirement embedded in Clause 20.1 of the FIDIC 1999 suite. Known colloquially as the “time-bar,” this clause has been the graveyard of otherwise meritorious claims, wiping out entitlements worth millions of dollars on technical grounds entirely unrelated to the merits of the underlying claim.

Construction Law, Contract Administration, Statutory Adjudication

Reflecting on the Second Edition of International Contractual and Statutory Adjudication

By Dr Samer Skaik

Over the past decade, my work in construction law and adjudication has consistently reinforced one reality: adjudication has become a cornerstone of modern dispute resolution across the global construction industry. It has therefore been a privilege to contribute to the Second Edition of International Contractual and Statutory Adjudication, as an Assistant Editor as well as a Contributor of six chapters, bringing together perspectives from across multiple jurisdictions. The book is edited by the prominent author & practitioner Andrew Burr with editorial assistance from Narudee Chuekitkumchorn and myself.

Construction Law, Contract Administration, Project Management

Decoding Concurrent Delay: The SCL Protocol and Employer Responsibility

Delays in construction and infrastructure projects are almost an inevitability. But what happens when multiple delays hit at once, and some are the client’s fault while others lie with the contractor? This is the tricky terrain of concurrent delay, a concept that can lead to significant disputes over extensions of time and financial compensation.

Construction Law, Contract Administration

Navigating the Tensions: A Guide to Mediation in Construction Disputes

Construction projects are inherently complex, often fraught with variables that can lead to disagreements, claims, and disputes. When a conflict arises, it can be costly in terms of time, money, and professional relationships. While a traditional approach might be to head straight to litigation, it is often more effective to leverage alternative dispute resolution (ADR) methods like negotiation and mediation. The key to success lies in understanding and managing three core tensions that exist in every dispute.

 

1. The Tension Between Creating Value and Distributing Value

In any dispute, there are two primary objectives: to create a larger “pie” of value that all parties can share, and to claim the largest possible slice of the existing pie for yourself.

• In a construction dispute, “creating value” means looking for a solution that benefits all parties beyond a simple financial settlement. This could involve agreeing to future collaboration, sharing a technical solution, or adjusting a project schedule to mitigate further costs for everyone.

• “Distributing value” is the more traditional, combative approach—arguing over who is owed what, based on the contract terms and legal positions. A successful negotiation or mediation requires parties to move beyond a purely distributive mindset. By focusing on creating value, such as a solution that keeps the project on track or preserves a long-term business relationship, parties can often achieve a better outcome than they would through a legal battle.

2. The Tension Between Empathy and Assertiveness

Effective dispute resolution requires a delicate balance between understanding the other side’s perspective and confidently advocating for your own.

• Empathy is about stepping into the other party’s shoes to understand their motivations, constraints, and fears. For a contractor, this might mean understanding the client’s financial pressures or the project manager’s need to meet a strict deadline.

• Assertiveness is about clearly and firmly articulating your position, rights, and interests. In construction, this involves knowing the contract language inside and out and being prepared to present a strong case for your claims.

Failing to manage this tension can derail a resolution. Too much assertiveness without empathy can lead to a stalemate, while too much empathy can result in a disadvantageous settlement. The best approach is to be strong on your interests, but soft on the people.

3. The Tension Between Principals and Agents

This tension highlights the conflict between the direct stakeholders (the principals—e.g., the company owner or client) and their representatives (the agents—e.g., project managers, superintendent, legal counsel).

• In a construction dispute, the agents are often the ones in the negotiation room, but they are not the ones who will ultimately live with the consequences of the resolution. Their incentives might be different from the principals’. A lawyer might be incentivized to pursue a case to trial, while a company owner might simply want the dispute to go away.

• Disputes often become more difficult to solve when the principals are not present or involved in the process. It is crucial for agents to have a clear understanding of their principals’ true interests and to ensure that a resolution aligns with those goals. The most successful mediations often include direct involvement from the decision-makers on both sides.

By keeping these three tensions in mind, parties involved in construction disputes can move beyond positional bargaining and work toward a collaborative solution that saves time, money, and most importantly, preserves critical business relationships.

Watch this related video:

: https://youtu.be/fS0T-Bbq5tU?si=xqL1B3vyIGovvHIg

Construction Law, Contract Administration

The Crucial Choice: One or Three Decision Makers in Construction Disputes

A fundamental question often arises at the heart of dispute resolution planning: should a dispute be decided by a single individual or a multi-member tribunal? This choice carries profound implications for speed, cost, expertise, and the ultimate robustness of the decision. This post delves into the arguments for each approach across various dispute resolution mechanisms, offering insights to inform this critical decision.

Construction Law, Contract Administration

Dispute Boards in Construction: Enforcement and Governing Law

Construction projects are complex undertakings, breeding grounds for disagreements that can escalate into costly, project-derailing disputes. For decades, the industry has sought better ways to resolve conflicts without resorting to lengthy arbitration or litigation. Enter the Dispute Board (DB), a project-based, real-time resolution mechanism designed to keep projects moving and relationships intact.

However, the power of a Dispute Board decision is not absolute. Its real-world teeth depend heavily on a crucial, often overlooked factor: the governing law of the contract. This article dives into the world of Dispute Boards, exploring how they function, how their decisions are enforced, and how the choice of jurisdiction can make or break their effectiveness, especially when compared to the statutory adjudication process.

Scroll to Top