<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
		>
<channel>
	<title>Comments on: Ask CMGUIDE</title>
	<atom:link href="http://www.cmguide.org/ask-a-question/feed" rel="self" type="application/rss+xml" />
	<link>http://www.cmguide.org</link>
	<description>All you need for your career..</description>
	<lastBuildDate>Thu, 26 Jan 2012 11:12:34 +0000</lastBuildDate>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
	<generator>http://wordpress.org/?v=3.3.1</generator>
	<item>
		<title>By: mathewaugusty</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12408</link>
		<dc:creator>mathewaugusty</dc:creator>
		<pubDate>Thu, 26 Jan 2012 11:12:34 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12408</guid>
		<description>Dear Sir,
Once penalty for delay in completion is applied to the Contractor and paid by them, then wheather he has the right get back the guarantee amount? And one year maintenance period also he can avoid?</description>
		<content:encoded><![CDATA[<p>Dear Sir,<br />
Once penalty for delay in completion is applied to the Contractor and paid by them, then wheather he has the right get back the guarantee amount? And one year maintenance period also he can avoid?</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: jamesbaldesco</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12407</link>
		<dc:creator>jamesbaldesco</dc:creator>
		<pubDate>Tue, 24 Jan 2012 06:41:58 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12407</guid>
		<description>Thanks for all your Answers Srinivas and Mr. Samer..</description>
		<content:encoded><![CDATA[<p>Thanks for all your Answers Srinivas and Mr. Samer..</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: m_owies</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12406</link>
		<dc:creator>m_owies</dc:creator>
		<pubDate>Sun, 22 Jan 2012 14:59:25 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12406</guid>
		<description>for example UOM for ductwork for HVAC is shown  in Item not in LM. nor SF and the estimator&#039;s killing mistake he put his price for the item based on LM !! (Fidic 1987 rev. in 1992)</description>
		<content:encoded><![CDATA[<p>for example UOM for ductwork for HVAC is shown  in Item not in LM. nor SF and the estimator&#8217;s killing mistake he put his price for the item based on LM !! (Fidic 1987 rev. in 1992)</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: m_owies</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12405</link>
		<dc:creator>m_owies</dc:creator>
		<pubDate>Sun, 22 Jan 2012 14:50:33 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12405</guid>
		<description>Thank you v. much for your clear advice ,

let&#039;s go a little far for the same case ,what if the contractual completion date for that project had already expired while the contractor still didn&#039;t even start to complete those omitted items , what will be the contror&#039; entitlement to claim in such condition?</description>
		<content:encoded><![CDATA[<p>Thank you v. much for your clear advice ,</p>
<p>let&#8217;s go a little far for the same case ,what if the contractual completion date for that project had already expired while the contractor still didn&#8217;t even start to complete those omitted items , what will be the contror&#8217; entitlement to claim in such condition?</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: Ayman Eleish</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12404</link>
		<dc:creator>Ayman Eleish</dc:creator>
		<pubDate>Sun, 22 Jan 2012 11:27:23 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12404</guid>
		<description>Actually it is not under fidic,but I would like to know the fidic opinion in that regards,it is re-measured contract.
Thanks and Regrads,</description>
		<content:encoded><![CDATA[<p>Actually it is not under fidic,but I would like to know the fidic opinion in that regards,it is re-measured contract.<br />
Thanks and Regrads,</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: Samer Hisham Skaik</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12403</link>
		<dc:creator>Samer Hisham Skaik</dc:creator>
		<pubDate>Sun, 22 Jan 2012 11:23:17 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12403</guid>
		<description>There is no clause giving you the entitlement to vary the rate under such circumstances following FIDIC 1987.

Under FIDIC 1999, please refer to clause 12.3 which explains the circumstances of varying the rate and I believe your case is covered.</description>
		<content:encoded><![CDATA[<p>There is no clause giving you the entitlement to vary the rate under such circumstances following FIDIC 1987.</p>
<p>Under FIDIC 1999, please refer to clause 12.3 which explains the circumstances of varying the rate and I believe your case is covered.</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: Samer Hisham Skaik</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12402</link>
		<dc:creator>Samer Hisham Skaik</dc:creator>
		<pubDate>Sun, 22 Jan 2012 11:18:14 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12402</guid>
		<description>which form of contract do you use?</description>
		<content:encoded><![CDATA[<p>which form of contract do you use?</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: Samer Hisham Skaik</title>
		<link>http://www.cmguide.org/ask-a-question/comment-page-11#comment-12401</link>
		<dc:creator>Samer Hisham Skaik</dc:creator>
		<pubDate>Sun, 22 Jan 2012 11:17:07 +0000</pubDate>
		<guid isPermaLink="false">http://cmguide.org/?page_id=308#comment-12401</guid>
		<description>Please give me more details about the mistake you refer to.</description>
		<content:encoded><![CDATA[<p>Please give me more details about the mistake you refer to.</p>
]]></content:encoded>