Post Contract Construction
The change from pre-construction to the construction stage reflects all the preparation required to define your project that allows the construction work to start on site. (Read more..)
Comments (1) | 8,410 views |
Comments (1) | 8,410 views |
On demand’ guarantee bonds are a typical form of contractual security in the UAE construction industry, particularly on large projects. Their use in theory, is to afford the employer with secured funds from a surety, in the event the defaulting party does not perform under a contract or becomes insolvent.
Prior to the onset of the liquidity crisis last year, the general attitude of an employer (as a beneficiary) would have been to threaten the encashment of a bond to impose commercial pressure on a contractor to perform. A call upon an on-demand bond would have been made if strictly necessary e.g. in the event of material or persistent default. (Read more..)
Comments (2) | 3,608 views |
There are two major definitions for configuration management.
Leave a Comment | 2,173 views |
When estimating effort hours, duration and cost, you must start off with an estimate of effort hours. Without an idea of the effort hours, you cannot accurately estimate duration or cost. (Read more..)
Comments (1) | 6,289 views |
Implement “Zero Tolerance” Scope Change Management
This technique can be applied to help remedy a project that is either over deadline or over budget. Many projects begin to trend over their budget because they are doing more work than they originally committed to as a result of poor scope change management. If you are at risk of missing your budget, the project manager must work with the client and team members to ensure that absolutely no unplanned work is being requested or worked on – even if it is just one hour – unless formal scope change management is invoked. To repeat – this does not mean that there can be no more scope change requests. It simply means that EVERY scope change request must go through scope change management (which should be happening anyway). All other energy should go into cutting costs and completing only the core work that was agreed to. (Read more..)
Comments (1) | 1,777 views |
During the life-cycle of a construction project, most contractors routinely predict in some fashion the project’s final job costs to determine whether it will be in a profit or loss position at completion. If these predictions are frequent, accurate and timely, the contractor can also often identify job problems, take appropriate action and mitigate or eliminate potential economic loss while the project is underway. Armed with this information, a contractor can make critical business decisions more confidently. (Read more..)
Comments (1) | 4,035 views |
The following techniques can be used at the project level or activity level, or for any sized work in-between. (Read more..)
Comments (1) | 4,755 views |
Sometimes the project manager can get too comfortable (or too uncomfortable) in how the project is progressing. In many cases, it makes sense to have an outside party come in to evaluate the project management processes being utilized and double-check that the project is progressing as expected. This “outside party” could be any qualified person outside of the project manager. (Read more..)
Leave a Comment | 2,330 views |
Projects, especially larger ones, are never executed exactly as they are planned. Some activities finish early. Some finish late. Sometimes it is not easy to know if you are ahead of schedule or behind. Likewise, sometimes it is hard to know whether you are under budget or not. (Read more..)
Leave a Comment | 1,422 views |