Contract Administration

Construction Law, Contract Administration

FIDIC’s Middle Eastern Contract Users’ conference returns for a 3rd year!

This is your annual opportunity to get best practice advice on using the FIDIC contracts and updates on the contract changes and amendments – directly from the very people who drafted them!

Get a 10% discount with VIP code: FKW82257CMGP1 – and if you book by the end next Thursday 15th December you’ll get the lowest early bird prices as well. …

Contract Administration

Variations in Construction Contracts

Variations in Construction Contracts

Variations in construction contracts can mean changes to the terms of the contract or it can mean changes to the scope or character of the works. In this article, Lim Chuen Ren looks at variations in construction contracts in the latter sense.

Variations to the scope of construction works are necessary because no project is impeccable and changes are required to meet unforeseen circumstances or changed requirements. Thus, variation can be in the form of additions, omissions or substitutions.

Functions of Variations Clauses

Variation clauses are a common feature in construction contracts. It is useful to note, at the outset, that the proprietor is not entitled as of right to direct variations (Ashwell Nesbitt v Allan & Co (1912) Hudson’s Building Contracts (4th ed) Vol 2 at page 462). Hence the need for a variation clause. Secondly, they ensure that contractors can recover payments for variations properly directed (Knight Gilbert Partners v Knight (1968) All ER 248).

Issues Concerning Variation

Broadly, problems concerning variations arise in three areas:

scope (was it a variation or was the contractor bound to do it anyway?);
non-compliance with procedural requirements; and
valuing the variations.
Whether the variation work is within the scope of the contract will depend, firstly, on the terms of the contract, which sometimes beg the question: what is the contract? In many cases, the documents forming the contract are defined. An example is clause 1.1 of PC-1 (PC-1, 1988 Project Contract by Property Council of Australia) which provides:

Contract

The contractual relationship between the parties is constituted by:

(a) the Formal Agreement to which these Conditions of Contract are attached;
(b) these Conditions of Contract;
(c) the Contract Particulars;
(d) the Works Description; and
(e) the other documents (if any) referred to in the Contract Particulars.

Even without such explicit provisions, it is probably true to say that the court will not confine itself to the written agreement alone in determining the scope of the contract: specifications, drawings, correspondence, etc, all form part and parcel of the contract.

Having determined the contract documents, there is the further issue of inconsistencies in or between parts of the contract. Different contracts deal with the issue differently. FIDIC, in clause 5(2), provides for a priority list of documents as follows:

The several documents forming the Contract are to be taken as mutually explanatory of one another, but in the case of ambiguities or discrepancies the same shall be explained and adjusted by the Engineer who shall thereupon issue to the contractor instructions thereon and in such event, unless otherwise provided in the contract, the priority of the documents forming the contract shall be as follows:

(i) The contract Agreement (if completed).
(ii) The Letter of Acceptance.
(iii) The Tender.
(iv) Part II of these conditions.
(v)  Part I of these conditions.
(vi) Any other document forming part of the Contract.

The JCC-D 1994 contract (section 2, JCC-D 1994 Building Works Contract without Quantities issued by the Joint Contracts Committee, Australia) provides for a similar precedence of contract documents but goes one step further by requiring the contractor or architect, if they discover any discrepancy, to inform the other. The architect will then give to the contractor an instruction explaining, determining or correcting the discrepancy.

Implied or Necessary Works

As indicated, whether a particular work is a variation will depend on whether it comes within the general scope of the contract. Some works, although not specifically described, are nevertheless considered as implied or form a necessary part of the contract. An early case on this point is Williams v Fitzmaurice (1858) 157 ER 709. In that case, the contractor undertook to provide ‘the whole of the material mentioned or otherwise in the foregoing particulars necessary for the completion of the work’ and ‘to perform all works of every kind mentioned and contained in the foregoing specifications for the sum of 100.00 pounds’. Flooring was not specifically mentioned and the issue was whether it was included in the contract. The court held that it was.

Similarly, in Walker v Randwick Municipal Council (1929) SR (NSW) 84 the contractor agreed to ‘do and perform the whole of the works required in or about the construction of a concrete retaining wall’. In performing the works, Walker had to remove a sandbank to construct the retaining wall. The plan (which was not incorporated in the contract) showed the bank to be 6 feet wide. Walker claimed the bank was in fact 12 feet wide and claimed for work and labour in removing the extra 6 feet. The majority of the court held that the contract was an entire one to build a retaining wall at a fixed price and that the risk lay with contractor. Rogers J said (at page 87):

The contract is not to perform the work set out in any plan; all work necessarily required for the construction must be done whether set out in the plan or not.

Formal Requirements – Written Directions

A variation is usually effected through an instruction from the principal’s architect or superintendent. Such instructions are usually required to be in writing. Whether this is a pre-requisite to the contractor’s right to recover payment will depend on whether the requirement is a condition precedent. This is a matter of interpretation of the contract. Lord Blackburn in District Road Board of Broadmeadows v Mitchell (1867) 4 WW & A’B (L) 101 (FC) has this comment:

It is common enough to have provisions, as these are here, more or less stringent, saying that no extra work shall be paid for unless it is ordered in writing by the engineer, and if such conditions are properly made, and there is nothing fraudulent or iniquitous in the way they are carried out, these conditions would be quite sufficient and effectual (Tharsis Sulphur & Copper Co v M’elvoy & Sons (1878) 3 AC 1040 at pages 1050-1051).

What constitutes ‘writing’ is sometimes also an issue. In Wormald Engineering Ltd v Resources Conservation Co (1992) 8 BCL 158, sketches in the architect’s office describing the variations to be done was held not to be sufficient to satisfy the clause requiring alterations to be directed in writing in the architect’s hand, but in Bedford v Borough Of Cudgegong (1900) 16 WN (NSW) 142, a letter signed by the architect authorising the work was held to be sufficient.

Recovery in the Absence of a Written Direction

Whilst failure to comply, on the whole bars, a claim, there have been cases where courts have allowed the contractors to recover on the basis of an implied promise to pay: Liebe v Molloy (1906) 4 CLR 347, or estoppel: Update Constructions Pty Ltd v Rozelle Child Care Centre (1990) 20 NSWLR 251, or on the basis of unjust enrichment – standing by and taking the benefits: Hill v South Staffs Railway (1865) 12 LT (NS) 63, or on the basis that the works ordered are outside the scope of the contract and, therefore, constitutes a separate contract: Pavey & Mathews v Paul (1987) 61 ALJR 151.

Limitations on the Power to Vary

Variation clauses, even if widely drafted, nevertheless have limitations. One such limitation is the issuance of the practical certificate of completion. Commissioner of State Bank v Constain (1983) 3 ACLR 1 illustrates the point that the power to order variations is not in force after the certificate of practical completion as it then reaches the stage for maintenance and rectification of defects. This restriction is now reflected in AS 4000 Clause 40.

Secondly, the contractor is not required to undertake works that are outside the scope of the variation clause itself. As Cook J in J & W Jamieson Construction v City Of Christchurch (unreported, 8 November 1984, Christchurch High Court) said:

To my mind, if a variation may fairly be said to be a change to the works as these described, whether it comprised an addition, reduction or substitution to the works or effects the carrying out of the works, then it is a variation which the contractor is under an obligation to carry out, if it is beyond that, it is not.

A third limitation that is sometimes canvassed is this. A variation is defined as something which bears some relationship to the current contract works (Blue Circle Industries plc v Holland Dredging Co Ltd 37 BLR 40 per Purchas LJ). Thus, the variations directed must be ‘of a character and extent contemplated by, and capable of being carried out under, the provisions of the contract’ (AS 4000 Clause 36.1). A similar qualification is to be found in the JCCD 1994 Contract, Clause 6.10.01 (‘Unless otherwise agreed all Variations shall be within the general scope of this Agreement so as to be of a character and extent contemplated by and capable of being executed under the applicable conditions of this Agreement.’). Clauses like these prevent the proprietor from effecting fundamental changes to the building design or works under the guise of variations.

Other limitations relate to the right of the proprietor to omit works from the contractor. Generally, the power to vary the scope of works does not allow a proprietor to deprive the contractor of the benefit of that work altogether. In Commissioner of Main Roads v Reid [1974] 131 CLR 378 (see also JA Berriman v Carr (1953) 89 CLR 327), a clause in the contract allowed that:

if sufficient topsoil to meet the requirements of the works cannot be obtained within the right-of-way, the engineer may direct the contractor in writing to obtain top soil from other approved locations.

The contract also contained a clause allowing the engineer to omit any of the works. The engineer, instead of allowing the contractor to obtain the required topsoil from other approved locations, decided to omit the works from the contractor and awarded the works to another contractor, at a cheaper rate. The High Court of Australia held that the clause only gave the engineer the choice between directing the contractor to obtain the topsoil or to omit the works. It did not confer on the engineer the right to have the works performed by a third party.

Stephen J (at page 382) made the point that:

Were he [the engineer] legally entitled to do so it would, I think, run counter to a concept basic to the contract, namely that the contractor, as successful tenderer, should have the opportunity of performing the whole of the contract works.

Chadmax v Hansen & Yunken Pty Ltd (1985) BCL 52 is a case that illustrates the dilemma sometimes faced by the main contractor when compelled by the proprietors to omit certain works. In this case, the subcontractor was engaged to install ‘wallflex’ to stairwells and corridors. The architect subsequently deleted a substantial portion of that particular work from the main contract and the main contractor did likewise with the subcontract. The subcontractor sued the main contractor for repudiation of contract and succeeded. The judge in the first instance, Brebner J, commented that:

I would have held that the power in the defendant to require increases or decreases in or omissions from the sub-contract work or changes in the character or quality of any material a work could not be construed as a power to cancel virtually the whole of the subcontract works.

The main contractor joined the owners as a party to the action but, unfortunately for the main contractor, the ‘wallflex’ works in the main contract constituted only a minor part and their omission from the main contract was held to be within the general scope of the contract.

Valuing the Variation

If the variation falls within the terms of the contract, the rates prescribed will be used to value the work. Clause 36.4 of AS 4000 is one such clause, which also allows a reasonable sum for profits:

36.4 Pricing
The Superintendent shall, as soon as possible, price each variation using the following order of precedence:

prior agreement;
applicable rates or prices in the contract;
rates or prices in a priced bill of quantities, schedule of rates or schedule of prices, even though not contract documents, to the extent that it is reasonable to use them; and
reasonable rates or prices, which shall include a reasonable amount for profit but not overheads.
That price shall be added to or deducted from the contract sum.

In most cases, valuation using the rates prescribed in the contract presents no real problem. But what is the position if the contract is terminated or if the works are carried out under a separate, and usually oral, contract? In such cases, the courts will usually award a reasonable rate or a rate on a quantum meruit basis. As Giles J said in Atlantic Civil Pty Ltd v Water Administration Ministerial Corpn (unreported, 16 October 1992, NSW Supreme Court):

… [A] variation was to be valued in accordance with schedule rates so far as applicable or, in the absence of agreement, by determining a reasonable rate a price. No doubt the referee considered that the Schedule rates were inapplicable, and when he referred to ‘a quantum meruit basis under the contract’ I consider that he meant a reasonable sum for the additional work. Thus, the referee was not assessing a sum outside and in defiance of the contract. In my opinion the defendant’s submission was based on a misconception of the report.

Conclusion

Variation is almost an inevitable part of any construction claim. Given the competitive environment that the construction industry is usually in, many contractors probably rely on the proprietor’s variations to make a reasonable return for their contracts. In addition, variation works commonly affect the completion date and, therefore, impact on delay claims by the proprietor. This explains, to some extent, why the resolution of issues concerning variations is never easy, especially if the dispute is heard way after the building is completed and records are scarce, making physical measurement of the works completed difficult.

Lim Chuen Ren
CR Lim Construction Lawyers, Melbourne

Construction Law, Contract Administration

Incorporation by Reference

What is ‘incorporation by reference’? Put simply, it is a means by which the parties to a contract make reference to a standard form of contract conditions, technical specifications or similar publication without the need of having to retype the whole of that document in order for it to form part of the documentation which together forms the contract between the parties. …

Construction Law, Contract Administration

On-demand bonds are not foolproof

KATIE LISZKA* looks at the circumstances in which the beneficiary of an on-demand performance bond may be prevented from calling on the bond for reasons outside the terms and conditions of the bond itself.

THE recent global financial crisis has brought the performance security documentation provided on construction projects into sharper focus. Employers are looking to protect themselves should current and future projects get into trouble and are considering more carefully the security provided.
Unfortunately, some parties are in the position of having to consider what terms they signed up to in better times and whether or not they can enforce the security. An employer commonly requires a performance bond and, where there is a parent company, a parent company guarantee, as security for the performance of the contractor’s obligations. These requirements are usually contractual obligations in the underlying construction and engineering contract. Of the different types of bond available, the on-demand performance bond offers the employer the most robust form of protection.

It is worth considering the purpose of an on-demand bond and the advantage it offers to an employer. The key advantage is that the bond can be called even if there is an underlying dispute under the contract, allowing the employer ready access to cash. An on-demand bond operating in this way is also advantageous for the bondsman as it does not want to be concerned with merits of the underlying claim in respect of which the call is made. But does on-demand always mean on-demand?

If it doesn’t mean “when requested” and requires something more, the commonly perceived benefits are potentially seriously undermined. This article considers two cases, one in the Special Tribunal related to Dubai World and the other an English case in the Technology and Construction Court. Both case concern interim applications to restrain the employer from calling on an on-demand performance bond. In both cases, the applications were successful and the employers prevented from making the calls.

Recent cases

Simon Carves Limited v Ensus UK Limited [2011] EWHC 657 (TCC) relates to a process plant to produce bioethanol at a site in Teesside, in the north-east of England. The contract was an IChemE Red Book, as amended by special conditions agreed between the parties. The special conditions of the contract obliged Simon Carves to provide a performance bond “as security for all and any of the contractor’s obligations and liabilities under the contract…” The bond would become null and void, save for any pending or previously notified claims, on issue of the acceptance certificate. The contract also provided for the return of the bond once it had become null and void, save where there were pending claims. The word “claim” was not defined in the contract. However, there was a clause which stated that any claim “shall be supported by a written statement of the grounds and summary of material facts upon which it is based”.

The acceptance certificate was issued, “subject to outstanding defects being rectified as per the attached schedule and subject to resolution of liability of certain of the rectification works…” As the acceptance certificate had been issued, Simon Carves claimed that the performance bond was null and void and should be returned. Ensus UK’s position was that arguably there was a “claim” in the form of the list of defects and the bond, therefore, should not be returned.

The decision in this case confirmed, amongst other things, the following:

• Fraud is not the only ground on which a call on an on-demand bond can be restrained;

• If the underlying contract clearly and expressly prevents the beneficiary of the bond from making a demand, the beneficiary can be restrained from making a call on the bond; and

• At the interim injunction stage, the court has to be satisfied that the party seeking the injunction against the beneficiary of the bond has a strong case.

The judge granted the injunction on the grounds that Simon Carves had a strong case that the bond should be treated as null and void under the terms of the underlying contract. This was regardless of the fact that a call on the bond, as between the beneficiary and the bondsman, remained valid. This decision does not undo the principle that the bondsman need not be concerned with the provisions of the underlying contract. It does, however, mean that close attention should be paid by the employer to any terms in the underlying contract regarding the provision of and ability to call on the bond itself, as an employer may be prevented from calling on an on-demand performance bond if such a call is in breach of those terms. The Simon Carves case is clear that express provisions restricting a call are required.

The case of Bin Belaila Baytur General Contracting LLC v Nakheel PJSC and Standard Chartered Bank (DWT/APP25/ 003/2010) concerned two construction contracts relating to villa developments at Jumeirah village in Dubai, UAE. The contracts were governed by the laws of Dubai and the UAE, even though the documentation was drafted in English. Nakheel, the employer, was concerned about the slow progress of the works and issued formal notices under the contracts to that effect. It was also concerned that the contractor was short of money and Nakheel had directly paid a subcontractor. Nakheel at first delayed and then eventually ceased payment to Bin Belaila Baytur of amounts certified as payable under the contracts. Both parties purported to terminate the contract and what then developed was a dispute over who terminated the contracts and on what grounds. Nakheel then made a call on the performance bonds, for the full amount. However, before payment was made, Bin Belaila Baytur applied for an order restraining Nakheel from doing so before the final accounts had been finally determined.

In the proceedings, the judge framed the question as to whether Nakheel had bona fide legal grounds to justify its demand for payment of the full amount under the performance bonds. In answering this question, the court looked at the terms of the contracts, which limited the right to call on the bonds. The clause required the employer to give the contractor notice of “the nature of the default in respect of which the claim is to be made”. This clause was interpreted as restricting the right of the employer to call on the bond in situations where there is a bona fide claim for payment in respect of which the bond provides security, and to restrict the amount of the call to the amount of that bona fide claim for payment.

The court, in this case, was not satisfied that there were bona fide legal claims to justify the demand for payment. The judge went on to acknowledge that Nakheel had not served the appropriate notice and that the court thought that Nakheel should not have been in a better position than if it had served such notice. Again, the court was concerned with the provisions of the underlying contract which limited the right to make a demand on a bond.

Implications

What conclusions can be drawn from these decisions? Both decisions give effect to the parties’ underlying contract. The cases focus on preventing the employer from calling on the bonds in breach of contract rather than whether the employer is entitled to claim in accordance with the terms and conditions of the performance bond between it and the bondsman. So, the position of the bondsman in not having to interrogate the merits of the underlying claim in respect of which the call is made is preserved.

Even if the bond is on-demand and the demand is in accordance with the terms and conditions of the bond, the beneficiary may be restrained from making the demand if the underlying contract restricts it from doing so. During negotiation of the contract documents and prior to making a call on an existing on-demand performance bond, careful attention should be paid not only to the wording of the on-demand performance bond itself, which has been the primary focus in the past, but also to the terms of the underlying contract relating to the agreement of the contractor to provide such a bond and the circumstance in which it can be called. The best position for an employer is to have no restrictions on its ability to call on a bond. If it is unable to achieve this position, the restrictions should be carefully and unambiguously drafted to avoid the call being prevented in circumstances that the employer did not intend.

An employer needs to be aware of any restrictions in the underlying contract on the ability to call on the bond and how these may be interpreted or the employer may find that it does not have the security it thinks it has and on-demand does not in practice mean on-demand.

Gulf construction Online

Construction Industry, Construction Law, Construction Technology, Contract Administration, General Management, PMP Hints, Procurement Management, Project Management

Opening and Closing remarks of Construction Lifecycle Risk Management Conference

Construction Lifecycle Risk Management Conference

Date: 17th & 18th April 2011

Venue: Sheraton Abu Dhabi Hotel & Resort, Abu Dhabi, UAE

Welcome and Opening Remarks by the Chairperson, Samer H SkaikWelcome and Opening Remarks by the Chairperson Samer H Skaik

Ladies and Gentlemen,

Good morning.

I am delighted to join our speakers in welcoming you all and open this Conference on “Construction lifecycle Risk Management” in Abu Dhabi.

It gives me great pleasure and honor to chair this conference. I am so happy that we have in this hall, dedicated individuals from different backgrounds and expertise, from various industries across the GCC region. Those delegates who travelled for miles remind us how important this conference is. Thank you all for coming.

Contract Administration

RECORDS, RECORD, RECORDS – Importance for Contract Claim

Contract Requirement

Max Abrahamson in his book Engineering Law and The ICE Contract wrote

” A party to a dispute, particularly if there is an arbitration will learn three lessons (often too late) the importance of records, the importance of records and the importance of records”. This quotation came to mind recently when I read the judgement in the case of Attorney General for the Falkland islands v Gordon Forbes construction (Falklands) Limited. A contract was let for the construction of the infrastructure of the East Stanley Housing Development in the Falkland Islands using the FIDIC 4th Editions conditions.

Contract Administration, General Management

Head Office Overhead & Profit Claims – Why Hudson’s Formulae Failed Most of the Time?

If you are a contractor and having a delayed project (presumably not solely caused by you!), Head Office Overheads Contributions may be in your list for Loss and Expense claims. It is common for contractor to adopt the simplest and so called ‘accepted’ method of calculating such expenses hoping the other side will accept it too. …

Construction Law, Contract Administration

WHEN DOES A VARIATION IN CONSTRUCTION BECOME A SEPARATE CONTRACT?

Variations Clause
Most standard forms of contract include a clause under which the employer or his representative is able to issue an instruction to the contractor to vary the works which are described in the contract. A change in shape of the scheme, the introduction of different materials, revised timing and sequence are all usually provided for by the variations clause. It will also usually include a mechanism for evaluating the financial effect of the variation and there is normally provision for adjusting the completion date. In the absence of such a clause the employer could be in a difficulty should a variation to the works be required. The contractor could either refuse to carry out the work or undertake the work and insist upon payment on a quantum meruit or fair valuation basis. Calculation of the price for the extra work applying this method could involve payment well in excess of the contract rates. …

Construction Law, Contract Administration, Project Management, Statutory Adjudication

Importance of contractor progress payment terms

It has been said that an army marches on its stomach. Contractors and subcontractors in the construction industry run on cash. Lord Denning many years ago made the oft repeated phrase that cash flow is the lifeblood of the construction industry and this sentiment is still relevant today. Estimators when preparing tenders usually concentrate on building profits into the price. Of equal importance is the amount of working capital required to fund the contract and the need to keep the amount to a minimum. The payment terms are therefore crucial to every contractor and subcontractor. Certification and payment should be the subject of careful strategy and planning. …

Scroll to Top