Contract Administration

Construction Law, Contract Administration

Lenders look to limit risks on projects

By David Johnston

Project finance loans are provided against project cash flows, rather than the assets of the project company. Any risk to the project cash flows endangers the lender’s ability to recover the debt capital. The lender, therefore, needs to ensure that the terms of the project documents are satisfactory and will both facilitate and protect the project’s ability to generate the necessary revenue to satisfy the loan repayments, particularly where – as happens all too often – the project runs into difficulties. As part of this, the lender will seek to ensure that the risk allocation between the project company and any third parties is acceptable and, therefore, that the project is considered bankable.

Construction Law, Contract Administration, Procurement Management, Project Management

Lessons for GCC on concurrent delay

By David Johnston

DELAYS on engineering and construction projects are almost inevitable; the more complex the project, the more likely the prospect of delay, and the more chance of two or more delays occurring at or around the same time.

Where the contractor is culpable for the delay, for example, rectifying its own defective workmanship, it is usually not entitled to an extension of time. However, where an employer-caused delay occurs concurrently with the contractor’s culpable delay – for example, where the employer has instructed a variation, and assuming that each of these events is of approximately equal significance – is the contractor now entitled to an extension of time?

Various legal jurisdictions have struggled with this question and come to different positions. Some of these positions are set out in this article, as are some suggestions as to how this debate should inform approaches taken by employers to concurrent delay on construction projects in the GCC.

Construction Law, Contract Administration, Project Management

Termination for Construction Contracts

By Heba Osman
A common scenario: the Employer is not happy with the Contractor’s performance, whether because of failure to perform the works in the manner provided for in the Contract or because of some other breach of the Contract. The Employer picks up the Contract, which – in the UAE – is usually some modified FIDIC standard form, in search of the termination provision. Most such termination provisions require the Employer to send the Contractor a notice to correct the failure or the breach within a specified period. If the Contractor fails to correct the breach, then the Employer becomes entitled to terminate the Contract. The Employer, feeling confident of its legal position, sends the termination notice. The Employer is satisfied that it has correctly terminated the contract.

Construction Law, Contract Administration

Draft hybrid contract with care

By Martin Preston

TYPICALLY, the contract price under a construction contract will either be a lump sum or cost reimbursable.

Under a lump sum contract, the contractor is required to provide a fixed price for carrying out and completing the scope of work. The risk that the cost of completing the works is more than the lump sum price sits with the contractor, who will only be entitled to be paid more than the lump sum price if the employer varies the scope of the works or delays or obstructs the contractor in carrying out the works. …

Construction Law, Contract Administration, Procurement Management, Project Management

Closer look at fitness for purpose

By David Johnston

ONE of the issues that most vexes construction lawyers is that of the standard of care the contractor owes to the employer, that is the degree of skill and caution which the contractor must exercise under the building contract.

Contractors will seek to ensure that the duty of care required is one of “reasonable skill and care”. Under a “reasonable skill and care” obligation, the contractor is required to exhibit only the standard of care that could reasonably be expected of a competent contractor. Employers, on the other hand, will often demand a higher standard which will seek to ensure that the completed project will be fit for its intended purpose.

Under a “reasonable skill and care” obligation, it may still be possible for design-and-build contractors to avoid liability, even if the completed project is not fit for its intended purpose, so long as they have not failed to act with reasonable skill and care. If the higher fitness for purpose standard is imposed, however, the employer would not be required to prove negligence against the contractor in order to succeed in a claim, but would only have to show that the project did not function as it was intended to do (such intended use having been set out in the contract or otherwise having been made clear to the contractor).

Under English law, a design-and-build contractor is under an implied obligation to construct the project in such a way that it will be reasonably fit for its intended purpose where the employer relies on the contractor for the design, and where such purpose has been clearly intimated to the contractor. This position is reflected in the major standard forms which are widely used throughout the Middle East, including the Fidic (Fédération Internationale Des Ingénieurs-Conseils) Yellow and Silver Book forms. Even the Fidic Red Book, a “construct-only” contract, specifies at clause 4.1 that where “the Contract specifies that the Contractor shall design any part of the Permanent Works, then unless otherwise stated in the Particular Conditions … the Contractor shall be responsible for this part and it shall, when the works are completed, be fit for such purposes for which the part is intended as are specified in the Contract”.

While a fitness for purpose obligation will not be implied by law in Middle Eastern jurisdictions as in England and Wales, fitness for purpose obligations are relatively common, due in part to the prevalence of the Fidic forms referred to above. Another reason is the level of energy and industrial facilities constructed in the region, which perhaps lend themselves more to being described with reference to an intended use than other types of construction project.

Employers will contend that the wide acceptance of fitness for purpose obligations in the standard forms itself shows that it is a market standard position. Furthermore, the incorporation of such an obligation, they will argue, is fundamentally a fair one: where the project fails to function as required, the employer (and possibly its shareholders and funders) will be out of pocket. An argument based on principles of fairness or equity is likely to be particularly persuasive in the Middle East.

Contractors, however, are becoming increasingly resistant to these terms. They will argue that intended purposes are insufficiently clear and so constitute a risk that is difficult to quantify or manage. They will also argue that it is unfair that such terms should be included in design-and-build contracts since they would not necessarily be considered to be market standard features of design consultancy agreements, nor do they commonly feature in “construct only” contracts (save where the contractor is responsible for design, as with Fidic Red Book above). In addition, contractors may claim that the idea that the employer relies on the contractor for the design is, in modern practice, a legal fiction given that in many EPC (engineering, procurement and construction) projects the contractor’s practical design responsibility extends to checking, confirming and taking on the design proposed by the employer’s design team. The adoption of design risk is simply to ensure that the employer has a single point of responsibility in terms of design and construction risk to which it can turn in the event of a claim arising.

Perhaps the most compelling argument against assuming any fitness for purpose obligations, at least in practical terms, is insurability. A contractor who is subject to a fitness for purpose obligation may find that such an obligation is not covered under its professional indemnity insurance policy. While the cover is not invalidated by the fitness for purpose obligation, such an obligation would usually fall outside the scope of a professional indemnity insurance policy. However, this might be seen as a risk that the contractor could best manage through the wording of its insurance policies and its relationship with its insurers, rather than the drafting of the warranties in the construction contract.

Negotiations over this small, but important, point can become fraught. In some, less complicated design-and-build projects, a fitness for purpose obligation may be helpful in establishing an appropriate duty of care. However, the parties on more complex projects, especially EPC projects, may find that the arguments over the standard of care can, to a certain extent, be avoided by setting out very clearly in the contract what is required of the completed project, not in terms of its use or purpose, but in terms of its performance. Properly drafted output or performance specifications, performance guarantees and testing and certification procedures should ensure that the contractor carries out the design and performs all other obligations in order to meet the output or performance specification. Such terms, provided they are accurately and comprehensively set out in the contract, may even obviate altogether the need for extended discussions over the required standard of care.

 

Gulf Construction

 

Contract Administration, Project Management

Managing Payment Delays on International Construction Projects

(The following outline was used in a presentation to the Overseas Construction Association of Japan, Inc. (OCAJI) The Dynamics of Payment

As a construction project moves toward completion, the Contractor loses leverage, and the Employer gains leverage.

This is based on the reality that the Contractor builds the project, and the Employer simply pays money. As the project nears completion, the Contractor has less leverage because the Employer is close to obtaining what he bargained for – a completed project. This is the time when the Employer will be inclined to suspend or reduce payments to the Contractor, not early in the Project.  …

Construction Law, Contract Administration

Consultants’ Fee Claims To Be Time-Barred in the UAE

By Michael Grose

As the fifth anniversary of the onset of the financial crisis approaches, engineers, architects and other consultants to the construction industry should be aware of the potential risk that this unhappy anniversary presents to any remaining fee claims. Whilst any expectation of payment at this late stage is likely to be low, any optimism that early signs of returning confidence might provide a chance to cash in old debts should take into account one of the more obscure time limits applicable under UAE Laws. …

Construction Law, Contract Administration, General Management, Project Management

Construction Law Summer School – IBC Legal’s 13th Annual Conference

“An international fiesta for construction industry professionals.”

 Join your international peers at IBC Legal’s most comprehensive construction law event for 3 days of intensive learning and networking

Construction Law Summer School – IBC Legal’s 13th Annual Conference

3rd – 5th September 2013 – Downing College, Cambridge University, UK

CMguide readers get a 10% saving …

Construction Industry, Construction Law, Contract Administration, Project Management

Top Tips For Handling Disputes In The UAE

by Richard Bell and James Fox

No business wants to enter into a dispute. Disputes are often costly, tie up management time and distract staff from profitable work. In the UAE where a civil dispute is sometimes accompanied by a criminal complaint, a dispute can have a significant impact on key staff, including travel bans and the stress of facing criminal charges. Taking the right action from the beginning of a dispute can help to resolve the dispute faster, more efficiently and at less cost. …

Construction Law, Contract Administration, Procurement Management, Project Management

Bridging the contractual gap between an employer and a sub-contractor in the UAE

By Eric Teo

What are the rights of an employer in the event a nominated sub-contractor fails to deliver the standard or quality of material and workmanship that the employer had expected to receive? Common wisdom dictates that the employer would ordinarily seek recourse against the main contractor for the sub-contractor’s failure, but are there any alternatives?

To answer the above question we need to firstly understand that there are, in practice, two types of sub-contractors: domestic sub-contractors and nominated sub-contractors. Secondly, we should examine the contractual relationships between the three parties, i.e. the employer, the main contractor and the sub-contractor. …

Scroll to Top